Reviewed by Craig Hoebing, Capital Market Funds, LLC - CBK-2007014 - Commercial Mortgage Banker · Updated October 2026
Talk to Craig about your deal. Call (480) 495-8072 · Contact
A draw is not a second loan. It is a release of money already budgeted, after someone checks that the work is there. The OCC Comptroller's Handbook, Commercial Real Estate Lending, version 2.0, March 2022, opened November 11, 2026, describes disbursement controls in its construction chapter: inspections, documentation of progress, and a rule that funds should not be advanced unless they are used solely for the project being financed, as the draw request and the loan agreement state. It says the lender's title policy should be updated with each draw so the title company can confirm there is no outstanding lien. It names mechanics liens, from parties who supplied labor or materials, as the common form, and it notes that in some jurisdictions those liens can take priority over the bank. This note is general information from a bank examiner's handbook. It is not legal advice, not an appraisal, and not a term sheet. Counsel reads the lease or the loan agreement in front of you.
The statewide construction path, which is arrangement and not a draw desk, is Arizona construction. The budget line that pays interest during construction is interest reserves. Do not treat that reserve as a construction draw. A condition report on a building that already exists is property condition assessments, which is a different inspection from a draw inspection of new work.
The progress plan the handbook describes for commercial jobs
The handbook says a progress payment plan is normally used for commercial projects. The bank releases funds as phases are completed. It says the bank normally retains, or holds back, 10 to 20 percent of each payment to cover overruns or unpaid bills. That range is the handbook's description of a typical bank plan. It is not a holdback Capital Market Funds sets. The borrower requests payment with a draw request or certification that lists the phase and the cost category, and certifies that the funds are for the project and that suppliers and subcontractors have been paid. The handbook says the request should include waivers showing those parties were paid for the work completed. After the bank reviews the request and independently confirms the work, it disburses the costs incurred, less the holdback.
Before the final draw, the handbook lists three controls: waivers or releases from contractors, subcontractors, and suppliers; a final inspection that the project is complete and meets the specifications; and a certificate of occupancy from the building authority. The bank, or the inspector the bank hires, releases the money. Capital Market Funds does not inspect the site and does not wire the draw.
What this note leaves to the bank
The handbook also describes a standard payment plan it says is normally used for residential and smaller jobs. This page does not walk through a house schedule. The collateral here is a commercial building. A loan on raw land with no building going up is not a draw schedule. Capital Market Funds arranges an introduction to a construction lender. It is not that lender, not a HUD MAP lender, and not a Fannie Mae DUS lender. The document list that sits beside a closing, rather than beside a draw, is commercial loan documents.
The office is 7373 E Doubletree Ranch Rd #255, Scottsdale, AZ 85258. The phone is (480) 495-8072. NMLS 2691252 | Capital Market Funds, LLC - CBK-2007014 - Commercial Mortgage Banker.
Sources
Questions
- Who decides that a commercial draw can be released?
The lender, after the inspection and the title update the handbook describes. Capital Market Funds does not fund the draw and does not sign the inspection.
- Is the 10 to 20 percent holdback a Capital Market Funds requirement?
No. The handbook says a bank on a progress plan normally holds back that share of each payment. The loan agreement of the lender you are actually using controls the percentage.
- Is an interest reserve the same wire as a construction draw?
No. The handbook treats interest reserves as their own budget item. This site's interest-reserve note is the place for that bucket. A draw pays for work in place.
- Does a certificate of occupancy come before the last dollar?
The handbook lists the certificate of occupancy among the controls before the final draw and the release of the holdback. The building department issues it. We do not.
- Arizona construction financing
- Interest reserves, a different bucket
- Property condition assessments
- Commercial loan documents
- Life company loans, a possible takeout
- Ask about a construction file
Financing pages for this note
The loan and city pages closest to this subject. Capital Market Funds arranges the request from Scottsdale and is not the lender.
Talk to Craig about your deal. Call (480) 495-8072 · Contact